ATAGalleryConstructionAir › June 30th 2001
aircon010630_01.jpg
No further work seems to have taken place on the entrance to the lift hill tunnel section, although work is now going on in the station area.
aircon010630_02.jpg
In the loading station area, concrete is now appearing. Note how the middle section seems to be seperated away. Perhaps a different level of concrete in the middle of the station for machinery or perhaps theming.
aircon010630_03.jpg
An overall view of the lift hill tunnel shows that soil has been used to fill in the edges of the concrete, and work can be seen going on in the loading station.
aircon010630_04.jpg
It appears that the lift hill tunnel now is just awaiting steel.
aircon010630_05.jpg
The large seperate section of the tunnel waiting for coaster machinery and electronics.
     